Public Liaison Officer: 888-409-4220

Bridgeport Harbor Station

Bridgeport Harbor Station Staff

Karl Wintermeyer, BHS Station Manager
KARL WINTERMEYER
BHS Station Manager
Vincent Fiumidinisi, BH3 Plant Manager
VINCENT FIUMIDINISI
BHS 3 Plant Manager
Wendy Lara, Senior Site Administrator
WENDY LARA
Senior Site Administrator
Gino Lopez, Maintenance Support Technician
GINO LOPEZ
Maintenance Support Technician

Bridgeport Harbor Station 5 Project Team

Scott Matheson, PSEG BHS5 Project Director
SCOTT MATHESON
PSEG BHS 5 Project Director
Bill Gerardi, PSEG Project Management
BILL GERARDI
PSEG Project Management
Bob Maso, Construction Manager
BOB MASO
Construction Manager
Raymond Norregarrd, Site Civil Superintendent
RAYMOND NORREGAARD
Site Civil Superintendent
Greg Luger, Site Safety Manager
GREG LUGER
Site Safety Manager
Hugo Quintana, COL Liaison
HUGO QUINTANA
COL / Liaison
Madelene Helens, Site Administrator
MADELENE HELLENS
Site Administrator

Bridgeport Harbor Station History

PSEG Power Connecticut Bridgeport Harbor Unit 3

Bridgeport Harbor Station was originally owned and operated by United Illuminating Company and began providing critical energy needs to the industrial factories and businesses in the South West Connecticut area in 1957 with its first unit.

As the demand for electricity increased in the area, a second electrical generating unit was constructed in 1961 and later, two additional units were added in 1967 and 1968. United Illuminating retired the first unit at Bridgeport Harbor Station in the mid-1990’s.

In 1999, as part of the electrical deregulation requirements, United Illuminating divested of their electrical generation assets and Bridgeport Harbor Station was purchased by WISVEST LLC.  WISVEST owned and operated Bridgeport Harbor Station until purchased by PSEG Power Connecticut LLC in 2002.

During the early 2000’s Bridgeport Harbor Station Units 2, 3 & 4 provided electricity for the day-to-day electricity needs of the Bridgeport area as well as additional electricity during extremely hot or cold weather.

Unit 2 was a 170 Megawatt oil fired unit until it was retired in 2012.  Unit 3 was originally built as 410 Megawatt that could burn either oil or coal. In 2002, Unit 3 was modified to operate on low sulfur, environmentally friendly coal and in 2015 the oil burning capability was decommissioned.   Unit 3 continues to provide additional electricity to the Bridgeport area during extreme hot or cold weather periods.

Unit 4 is a 22 Megawatt Combustion Turbine that is capable of rapidly responding to emergency needs for electricity.

Both Unit 3 & 4 were instrumental in providing electrical generating capability for the Bridgeport region during Superstorm Sandy in 2012 and during the prolonged and extreme cold weather during the polar vortex in the winter of 2014.

The original Title V permit for the Bridgeport Harbor Station facility was issued in 2001, and the first renewal was issued in 2007.

On February 9, 2011, parent company PSEG submitted an application to renew the Title V permit for Bridgeport Harbor Station. The State Department of Energy & Environmental Protection (DEEP) issued its tentative determination to approve the permit application on January 13, 2012.

Upon receiving a request for an informational hearing on the pending outcome, DEEP held an informational hearing on May 14, 2012 in Bridgeport, and the public comment period closed on May 21, 2012.

A proposed Title V permit was issued on September 13, 2012 and was followed by a 45-day review process by the U.S. Environmental Protection Agency (EPA). EPA did not object to the proposed permit granting DEEP permission to issue the permit.